Soft X-Ray Beamline Delivery Record - including VLSPGM

Synchrotron FacilityBeamlineCompletion DateMajor ComponentsScope of Work
UVSOR (Japan) BL5 2014 Mirror chamber
Monochromator
Exit slit
Design and Engineering
Manufacturing
Installation
Optical Components
Vacuum Components
JASRI (Japan) SPring-8 BL25 August 2013 Mirror chamber
Monochromator
Exit slit
Design and Engineering
Manufacturing
Installation
Optical Components
Vacuum Components
ESRF (France) UPBL7 August 2013 Exit slit Design and Engineering
Manufacturing
Installation
KEK-Photon Factory (Japan) BL-2 April 2013 Mirror chamber
Monochromator
Exit slit
Design and Engineering
Manufacturing
Installation
ALBA (Spain) BOREAS September 2011 Mirror chamber
Monochromator
Exit slit
Design and Engineering
Manufacturing
Installation
Optical Components
Chubu SR (Japan) BL-7U August 2011 Mirror chamber
Monochromator
Exit slit
Design and Engineering
Manufacturing
Installation
Optical Components
SOLEIL (France) DEIMOS August 2009 Monochromator
Exit slit
Design and Engineering
Manufacturing
Installation
Vacuum Components
SPring-8 (Japan) BL-7LSU March 2009 Mirror chamber
Monochromator
Exit slit
Design and Engineering
Manufacturing
Vacuum Components
Optical Components
KEK-PF (Japan) BL-13 March 2009 Mirror chamber
Monochromator
Exit slit
Design and Engineering
Manufacturing
Installation
Saga Light Source (Japan) BL-10 December 2008 Mirror chamber
Monochromator
Exit slit
Design and Engineering
Manufacturing
Installation
Interlock and Control System
Vacuum Components
SOLEIL (France) Metrology and Tests March 2008 Monochromator
Exit slit
Design and Engineering
Manufacturing
Installation
Vacuum Components